Major Gas Replacement works for Rodley and Calverley
Published: 28 May 2024
These works have been planned in collaboration with Major Highway works along the A6120, Ring Road Farsley and Horsforth New Road
The works will be phased as follows:
1. A6120 Horsforth New Road – from Rodley Roundabout to 30m past the Leeds and Liverpool Canal Bridge – To facilitate this phase of work, there will be an inside lane closure in place from Horsforth towards Rodley Roundabout, between 0930 – 1530hrs, and from Rodley roundabout, towards Horsforth, there will a lane closure in place full time until approximately 10th June, followed by a contra flow to 30m past the Bridge, until approximately 17th June
NB: To help facilitate the initial lane closure from Rodley Roundabout towards Horsforth, the right turn lane to Bramley in the roundabout will become dedicated, this will help maximise traffic flow, and Horsforth bound traffic will be reduced to one lane
Location of this first phase of works - https://one.network/?GB138809224
2. A657 Rodley Lane towards Calverley from Rodley Roundabout to Hawthorn Drive - This phase of works will commence approximately 24th June and will take place on Rodley Lane towards Calverley from Rodley Roundabout to Hawthorn Drive, this will involve a full time one way road closure to traffic travelling from Calverley, the diversion will be down Calverley Lane from The Calverley Arms
Location of works - https://one.network/?GB138602424
3. A657 Rodley Lane / Town Gate and Carr Road - The final phase will be to continue up Rodley Lane / Town Gate and Carr Road with the use of 2 way / Multiway manually operated signals, and where possible, 2 way traffic flow will be maintained without the use of signals –
Location of works - https://one.network/?GB138603802 & https://one.network/?GB138623632
NB: These dates are subject to change depending on how the works progress
There will be unavoidable delays, especially during the peak times, however, we will closely monitor the works to ensure this is kept to a minimum, with a view to making changes as the work progresses if the situation can be improved,